Solar panel recycling regulation in Brazil: PNRS, Decree 10.240 and Ordinance MMA 1.560/2026

What Brazilian law requires from anyone who takes photovoltaic modules out of service, who is responsible for each stage and where the rules are still being written.

By , founder of SunR · 8 min read · Updated

Covered warehouse with a concrete floor and block walls, with about fifteen stacks of decommissioned photovoltaic modules on wooden pallets
Photovoltaic modules removed from the field, palletized and waiting for recycling.

The law that governs solar panel disposal in Brazil is the National Solid Waste Policy (PNRS, Law 12.305/2010): whoever generates the waste is responsible for it until its environmentally sound final destination. Photovoltaic panels are also on the list of electrical and electronic equipment in Decree 10.240/2020, the reverse logistics decree (Brazil's take-back system for end-of-life products), and the targets of that system remain in force in 2026 under Ordinance MMA 1.560/2026.

For a plant operator, the law comes down to three questions: are the modules in the waste management plan, did every load leave with an MTR, does every batch have a CDF.

The rules that govern solar panel disposal

None of these texts was written only for solar panels. Together, they set out who is responsible, which documents must exist and what happens to those who do not comply.

Federal rules in force in October 2026.
RuleWhat it saysWho it applies to
Law 12.305/2010 (PNRS)Generator responsibility, shared responsibility, waste management plan and reverse logistics for electrical and electronic equipmentAll waste generators and the product supply chain
Decree 10.936/2022Regulates the PNRS and establishes the waste transport manifest in Sinir (Brazil's national waste information system)Generators, reverse logistics systems and environmental agencies
Decree 10.240/2020Reverse logistics for household electrical and electronic equipment; photovoltaic panels in Annex IManufacturers, importers, distributors, retailers and consumers
Ordinance MMA 280/2020MTR mandatory since 2021 and CDF issued by the receiving facilityGenerator, transporter and receiving facility
Ordinance GM/MMA 1.560/2026Keeps the 2025 targets of Decree 10.240 in force in 2026 until a new regulationReverse logistics system for electrical and electronic equipment
Law 9.605/1998Criminal and administrative penalties for conduct harmful to the environmentAnyone who fails to comply with the PNRS
Timeline of solar panel disposal regulation in Brazil2010: PNRS (Law 12.305/2010): National Solid Waste Policy: generator responsibility and reverse logistics. 2020: Decree 10.240: Reverse logistics for electronics. 2023: PL 3.784/2023: Bill (PL) specific to solar panels, in the Senate. 2024: PL 998/2024, PL 2.672/2024 (MG): Bills in the federal Chamber and in the Minas Gerais state assembly. 2025: PL 391/2025 and MT state law: New bill in the Chamber; Mato Grosso passes Law 12.919/2025. 2026: Ordinance 1.560/2026, PL 753/2026: MMA (Environment Ministry) ordinance keeps reverse logistics targets during the review; new bill in the Chamber.PNRS (Law 12.305/2010)National Solid Waste Policy: generatorresponsibility and reverse logistics.2010Decree 10.240Reverse logistics for electronics.2020PL 3.784/2023Bill (PL) specific to solar panels, in theSenate.2023PL 998/2024, PL 2.672/2024 (MG)Bills in the federal Chamber and in theMinas Gerais state assembly.2024PL 391/2025 and MT state lawNew bill in the Chamber; Mato Grosso passesLaw 12.919/2025.2025Ordinance 1.560/2026, PL 753/2026MMA (Environment Ministry) ordinance keepsreverse logistics targets during thereview; new bill in the Chamber.2026
Rules and bills on solar panel disposal in Brazil, in chronological order.

PNRS: the generator is responsible for the waste

Under Law 12.305/2010 (in Portuguese), a generator is anyone who generates solid waste through their activities, including consumption (art. 3, IX). A plant that replaces modules broken by hail is a generator. An O&M company that removes defective modules may also be one, depending on the contract.

Art. 20 requires a solid waste management plan (PGRS) from anyone who generates hazardous waste or waste that, by its nature, composition or volume, is not comparable to household waste. The plan describes the origin, volume and characterization of the waste, including environmental liabilities (art. 21). Broken modules sitting in the yard are a liability and count toward that plan.

The article that weighs most is art. 27, § 1: hiring a company for collection, transport or final destination does not exempt the generator from liability for damage caused by improper management. If the contractor disappears with the batch, the problem goes back to the generator.

Truck with its side tarp open, loaded with photovoltaic modules stacked in batches on pallets and secured with straps, parked on a dirt yard
A batch of modules leaving for recycling: the generator's responsibility travels with it until the CDF.

Decree 10.240/2020: solar panels are on the electronics list

The PNRS requires manufacturers, importers, distributors and retailers of electrical and electronic equipment to set up reverse logistics (art. 33, VI), and Decree 10.240/2020 (in Portuguese) organizes that system for household use. "Photovoltaic panel" is in Annex I, the list of products. Annex II sets the targets, which reached 17% by weight of the products sold in 2025, the fifth year (art. 49, § 1).

The limit is in the decree itself. Household use means personal, residential or family use, exclusively by an individual (art. 3, XVII). Corporate, industrial or commercial use and large volumes from large generators are excluded (art. 5). For those cases, art. 6 allows reverse logistics to be arranged by contract with the product supply chain and requires the final destination to be set out in the generator's PGRS.

The result: a residential panel falls under the electronics system. A module from a solar plant follows the general rule of the PNRS.

Ordinance MMA 1.560/2026: targets kept while the rule is revised

The schedule in Decree 10.240 ended in 2025. Ordinance GM/MMA 1.560/2026 (in Portuguese), dated January 2 and published in Brazil's Official Gazette on January 5, 2026, kept the 2025 targets of Annex II of the decree for 2026 "until a new regulation is issued" ("até que sobrevenha novo regulamento"). The system remains bound to the same targets while the government prepares the new rule.

Decree 10.936/2022 and the documents that prove the destination

Decree 10.936/2022 (in Portuguese), the current regulation of the PNRS, requires those responsible for a PGRS to report every year on how the plan is being carried out (art. 58). The day-to-day document comes from Ordinance MMA 280/2020 (in Portuguese): since January 1, 2021, a generator subject to a PGRS issues a waste transport manifest (MTR) for each shipment, and the receiving facility issues the certificate of final disposal (CDF) in the same system. The step by step is in MTR, CDF and destination report (in Portuguese).

Who is responsible for what

The generator issues the MTR and is responsible until the final destination is proven. The other links in the chain are responsible for the part they carry out.

Who is responsible for what in solar panel disposalGenerator: Plant, EPC, O&M or company that owns the modules. Liable for the waste until disposal is proven (PNRS). Transporter: Moves the batch with the MTR (waste transport manifest) issued. Must be licensed to haul waste. Recycler: The licensed recycler. Receives and treats the batch, then issues the CDF (certificate of final disposal) and the batch report. Makers & sellers: Manufacturers, importers and retailers set up reverse logistics for household electronics (Decree 10.240/2020).GeneratorPlant, EPC, O&M orcompany that owns themodules. Liable for thewaste until disposal isproven (PNRS).TransporterMoves the batch with theMTR (waste transportmanifest) issued. Mustbe licensed to haulwaste.RecyclerThe licensed recycler.Receives and treats thebatch, then issues theCDF (certificate offinal disposal) and thebatch report.Makers & sellersManufacturers, importersand retailers set upreverse logistics forhousehold electronics(Decree 10.240/2020).
Who is responsible for what in the disposal of PV modules.

What the law requires from plants, EPCs and O&M companies

  1. Put the modules in the PGRS

    Origin, estimated volume, storage and final destination of discarded modules, including what has already piled up in the yard.

  2. Classify the waste

    The class defines storage, transport and the license required from the receiving facility. See the guide are solar panels hazardous waste? (in Portuguese).

  3. Define the generator in the contract

    In EPC and O&M contracts, put in writing who removes the modules, who issues the MTR and who keeps the documents.

  4. Hire a licensed receiving facility

    The license must cover receiving and treating the waste. Hiring does not transfer responsibility (art. 27).

  5. Issue an MTR for every load and keep the CDF

    Together with the batch report, the MTR and the CDF answer inspectors, lenders and ESG auditors.

Tall stack of pallets of photovoltaic modules wrapped in plastic film, stacked four levels high on a paver floor next to a warehouse
Palletized and wrapped modules: storage set out in the waste management plan.

What about solar panels at home

For household consumers, responsibility ends when the product is returned through reverse logistics (art. 28 of the PNRS). The path is to return the module through the electronics system, by contacting the installer or the retailer, or to hand it to a licensed recycler. Regular trash and construction debris dumpsters are not an option.

Check first whether the drop-off point accepts modules. A panel is large and heavy, and its glass cuts when it breaks, so most electronics collectors do not take them. SunR collects with no minimum volume and has drop-off points for small volumes in Porto Alegre, Araranguá, Florianópolis, Cascavel, São Carlos, São Paulo and Brasília. You drop the modules off at the nearest point, or they are collected at your address (check with us).

What happens to those who do not comply

Art. 51 of the PNRS refers violations to the penalties of Law 9.605/1998 (in Portuguese) and keeps the obligation to repair the damage, with or without fault. For hazardous waste, art. 56, § 1, II, of that law, added by the PNRS itself, covers anyone who stores, transports or disposes of waste in a way other than that set out in law or regulation.

In day-to-day practice, inspectors, lenders and auditors ask for the same thing: the document that shows where the modules went.

What is still being written

As of October 2026, there is no specific federal rule for modules from utility-scale plants and commercial systems. There are bills in Congress and in the Minas Gerais state legislature, tracked in bills on solar panels (in Portuguese), and the state of Mato Grosso already has Law 12.919/2025 (in Portuguese), which encourages reverse logistics for photovoltaic panels.

In 2025, the Ministry of Environment (MMA) also held a public consultation (in Portuguese) to replace Ordinance 280/2020, which regulates the MTR. Until the new rule is out, Ordinance 280 applies. There is no legal vacuum: anyone who removes modules from a plant needs to be able to show where they went.

Guides on this topic

The documents SunR delivers

SunR, the first photovoltaic panel recycler in Latin America, has been recycling modules since 2020 and works under state environmental licenses and in partnership with PV CYCLE, the European photovoltaic recycling association. Every collection leaves with an MTR. At the end, the client receives the CDF, a destination report with the quantity, weight, dates and destination of each material, and a video of the process.

The reverse logistics service serves everything from homes to utility-scale plants, and waste management for EPC and O&M standardizes the documents across projects.

+6,000 t
of modules contracted
+190,000
modules contracted
+360
pickups since 2020
+80%
mechanical recovery

Frequently asked questions

Is there a law requiring solar panels to be recycled in Brazil?

There is no specific federal law. The PNRS requires the generator to ensure an environmentally sound final destination, and photovoltaic panels are in Annex I of Decree 10.240/2020, on reverse logistics for electrical and electronic equipment.

Who is responsible for disposing of a solar plant's modules?

The waste generator, who is responsible until the final destination is proven. Hiring a collection or recycling company does not transfer that responsibility (art. 27 of the PNRS).

What did Ordinance MMA 1.560/2026 change?

It kept for 2026 the 2025 targets for reverse logistics of electrical and electronic equipment under Decree 10.240/2020, until a new regulation is issued.

Does Decree 10.240/2020 apply to solar plants?

Not directly. The decree's system covers household use. Modules from solar plants fall under the generator's responsibility in the PNRS, with the final destination set out in the waste management plan (art. 6 of the decree).

What do I need to do with solar panels at home?

Return them through the reverse logistics system, via the installer or the retailer, or hand them to a licensed recycler. SunR collects with no minimum volume and has drop-off points in seven cities.